Exercise 10-5(Algo) Working Backwards from Labor Variances [LO10-2]
The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below:
Standard Hours Standard Rate Standard Cost
Motor tune-up 2.50 $32.00 $80.00
The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 52 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune-ups:
Labor rate variance $ 300 F
Labor spending variance $ 340 U
Required:
1. Determine the number of actual labor-hours spent on tune-ups during the week.
2. Determine the actual hourly rate of pay for tune-ups last week. (Round your answer to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!