Question: Exercise 1: Suppose that 5 jobs will be processed on a single machine. The jobs are ready for processing at time. The other job characteristics


Exercise 1: Suppose that 5 jobs will be processed on a single machine. The jobs are ready for processing at time. The other job characteristics are as shown in the table below. (30 Points) Find the: Mean flow time. Average tardiness and number of tardy jobs using: I EDD (30 Points) Job Processing Time Due Date 4 10 20 B 20 30 C 1 10 D 16 6 8 Sequence the operations on two machines based on earliest due date. Calculate the mean flow time. (28 Points) I M1 M2