Question: Exercise # _ 1 ( used in EVM lecture ) Project Scenario: Scope of work: to make 2 0 drawings for kitchen remodeling. Project duration:

Exercise #_1(used in EVM lecture)
Project Scenario:
Scope of work: to make 20 drawings for kitchen remodeling.
Project duration: 4 weeks
Cost: $1000 is allocated for all twenty drawings, i.e., $50 per drawing.
Workers: one full-time worker is available for the whole four weeks.
More Related Details:
Each drawing has the same level of difficulty, needs the same effort, and takes the same time.
The cost is directly related to effort, i.e., hours worked have equal cost each.
Drawings are produced at an equal pace over the four weeks, i.e.,4 drawings per week.
So, in summary, we are planning to spend $250? week for 4 weeks to produce 5 drawings/week, and each cost $50 The percentage of work completed was measured by the number of drawings produced at the end of the measurement period.
Questions:
What is the planned value for the four weeks?
What is the planned budget for each drawing?
How do you assess project performance at a specific point in time?
Assess the performance at the end of week 2(i.e., halfway through the project). Note that by the end of the last day of week 2, we had produced only 8 drawings. The actual payments were $50 for the first 7 drawings and $70 for the eighth.
 Exercise #_1(used in EVM lecture) Project Scenario: Scope of work: to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!