Question: Exercise 15: Given the following financing project being considered by a venture firm, find the probability of completing the path with the longest expected duration

Exercise 15: Given the following financing project being considered by a venture firm, find the probability of completing the path with the longest expected duration by 17 weeks. By 24 weeks. By what date is management 90 percent sure that this path will be completed? Assignment 2 Time (weeks) Most Activity" Optimistic Likely Pessimistic 1-2: Collect firm 1 1 11 data 1-3: Analyze data 10 10 10 1-4: Determine need N 5 2-6: Determine 13 profitability 3-6: Evaluate risk 4 10 3-7: Interview owners 7 10 3-5: Check references 2 a N 4-5: Evaluate industry NON 00 ON 5-7: Evaluate economy 14 6-7: Decide funding If the venture firm can complete the project for the customer within 18 weeks, it will receive a bonus of $10,000. But if the project delays beyond 22 weeks, it must pay a penalty of $5,000 due to lost opportunity. If the firm can choose whether or not to bid on this project, what should its decision be if the project is only a breakeven one normally? Figure 8.15a shows the network
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts