Question: Exercise 2 - 1 Order Point Pershing, Inc. expects daily usage of 5 0 0 lbs of material X , an anticipated lead time of

Exercise 2-1
Order Point
Pershing, Inc. expects daily usage of 500 lbs of material X , an anticipated lead time of seven days, and a desired safety stock of 2,500Ibs.
a. Determine the order point.
$ Ibs. QUESTION 1
b. Determine the number of pounds to be issued from safety stock if the new order is four days late. $ lbs. QUESTION 2