Question: Exercise 2 :Early Start Duration Early Finish Late Start Slack Late Finish Task Name 2 A 5 H 3 B 8 I 5 C 1

Exercise 2:Early Start Duration Early Finish
Late Start Slack Late Finish
Task Name
2
A
5
H
3
B
8
I
5
C
1
D
7
J
5
K
8
L
2
M
3
F
3
N
1
E
5
G
1. Perform a Forward Pass and a Backward Pass of the network diagram above
2. Which Activities has the same Early Finish as they have Late Finish?
Note: The project starts on Day 0