Question: Exercise 2 The following information is available for a project of North Ash Holdings: - Budget authorised for scheduled work to be completed thus far

 Exercise 2 The following information is available for a project of

Exercise 2 The following information is available for a project of North Ash Holdings: - Budget authorised for scheduled work to be completed thus far is R125 000. - Value of work actually completed expressed in terms of the approved budget is R150 000. - Actual cost incurred to accomplish the work performed thus far is R120000. - Sum of all budgeted values determined for the work to be done on a project is R550 000