Question: Exercise 3: [15 marks] 05. Using the following information, develop the optimal-cost solution Project contare 200 SAR per day Activity Normal time Crashing potential (days)
Exercise 3: [15 marks] 05. Using the following information, develop the optimal-cost solution Project contare 200 SAR per day Activity Normal time Crashing potential (days) Cost per day to crash (SAR) 2 A B 4 3 1 3 100 120 80 2 4 4 -3 D E F G H 90 1 0 0 2 1 5 6 100 50 5 1. Fill the table below. 2. Graph the total costs for the plan and determine an optimum crashing plan. Exercise 3: [15 marks] 05. Using the following information, develop the optimal-cost solution Project contare 200 SAR per day Activity Normal time Crashing potential (days) Cost per day to crash (SAR) 2 A B 4 3 1 3 100 120 80 2 4 4 -3 D E F G H 90 1 0 0 2 1 5 6 100 50 5 1. Fill the table below. 2. Graph the total costs for the plan and determine an optimum crashing plan