Question: Exercise 3 (8 marks) If we have a project and the needed time for the project' activities is given in the table below. Use the

Exercise 3 (8 marks) If we have a project and the
Exercise 3 (8 marks) If we have a project and the needed time for the project' activities is given in the table below. Use the critical path method to answer the following: Activity Predecessor Duration in days 5 A B 2 B 4 D B 6 E CD 3 F E 6 Develop the critical path network. b. Show ES, EF, LS, LF, on the network c. What are the critical path activities? d. What are the slack time of the activities? . What is the completion time of the project