Question: Exercise 3 VAC Tables Exercise 3: Earned Value This is an Exercise about understanding Earned Value. the VAC. This is worth 5% of your final
Exercise 3 VAC Tables
Exercise 3: Earned Value
This is an Exercise about understanding Earned Value. the VAC.
This is worth 5% of your final grade.
There are 3 Projects and you have to calculate
Project A (3 pts.)
You are given the following data. Calculate the VAC (Variance at Completion) for two scenarios as listed below
Project Budget Duration Status EV
PV AC BAC =
A $400,000 90 days 60 days $140,000 $150,000 $178,000
1. Assume future budget estimates do not change
ETC =
EAC =
VAC =
2. Assume future costs continue at the same spending rate
ETC =
EAC =
VAC =
Project B (3 pts.)
You are given the following data. Calculate the VAC (Variance at Completion).
Project Budget Duration Status EV
PV AC BAC =
B $220,000 200
140 $180,000 $180,000 $174,000
1. Assume future budget estimates do not change
ETC = EAC = VAC =
2. Assume future costs continue at the same spending rate
ETC =
EAC =
VAC =
Project C (4 pts.)
You are given the following data. Calculate the VAC (Variance at Completion).
Project Budget Duration Status EV
PV AC BAC =
C $3,500,000 450
80 $600,000 $580,000 $923,000
1. Assume future budget estimates do not change
ETC =
EAC =
VAC =
2. Assume future costs continue at the same spending rate
ETC =
EAC =
VAC =
3. Look at the VAC results for Project C. Make a comment or recommendation regarding the ETC, EAC, and VAC.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
