Question: Exercise 5 - 2 7 ( Algo ) Methods of Estimating Costs: Engineering Estimates ( LO 5 - 1 , 2 ) Collingwood Contractors (

Exercise 5-27(Algo) Methods of Estimating Costs: Engineering Estimates (LO 5-1,2)
Collingwood Contractors (CC) designs and builds new model homes for individual customers. CC has developed a reputation in the
market for relatively upscale, unique designs with high-end finishings. CC has developed several formulas, which it uses to estimate
costs and provide price quotes for prospective buyers. These include costs for materials, labor, and other resources. Although multiple
configurations are possible for any house, CC uses three levels (or tiers) to represent increasing levels of luxury in terms of materials
used. In addition, the customer can choose among three levels of increasingly sophisticated appliances and other house equipment.
Finally, there is cost to bring utilities (electricity, water, and so on) to the house if required. Of course, these estimates are dependent
on the region of the country and whether the lot is located in a city or in a suburb or rural area. If the building site is in a city, a premium
is added based on the building and equipment costs. The following are the cost estimates for one region in the Northwest:
Required:
a. A customer has expressed interest in having CC build a Tier III, 6,200-square-foot home. The building site is a city lot and the
customer wants the Sapphire level equipment. Based on the engineering estimates above, what will such a house cost to build? No
additional utilities access is required.
b. Another customer has expressed interest in having CC build a smaller, Tier I, home, but with emerald-level equipment. This home
will be on a vacant lot in the country and require utilities access to be added. The customer has chosen a 3,900-square-foot design.
Based on the engineering estimates above, what will such a house cost to build?
Answer is complete but not entirely corrist.
Complete this question by entering your answers in the tabs below.
Another customer has expressed interest in having CC build a smaller, Tier I, home, but with emerald-level equipment. This
home will be on a vacant lot in the country and require utilities access to be added. The customer has chosen a 3,900-square-
foot design. Based on the engineering estimates above, what will such a house cost to build?
Design costs
$52,000
 Exercise 5-27(Algo) Methods of Estimating Costs: Engineering Estimates (LO 5-1,2) Collingwood

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!