Question: Exercise 5.2 : Percentage Completion Method XYZ continued to work on the JSOM III project in 2008. On December 31, 2008, XYZs accountant gathered the

Exercise 5.2: Percentage Completion Method

XYZ continued to work on the JSOM III project in 2008.

On December 31, 2008, XYZs accountant gathered the following details pertaining to the JSOM III building project for 2008.

2008

Costs incurred during the year

186

Estimated cost to complete

264

Invoices raised on UTD during the year

350

Cash collections from UTD

330

XYZs accounting period is the calendar year and XYZ uses the percentage completion method to recognize revenues.

Required:

  1. Compute the percentage of completion in 2008 for the JSOM III project.
  2. Record the transactions for 2008 pertaining to the JSOM III project in XYZs accounting books. Assume that all costs incurred during the year were paid in cash.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!