Question: Exercise 5.2 : Percentage Completion Method XYZ continued to work on the JSOM III project in 2008. On December 31, 2008, XYZs accountant gathered the
Exercise 5.2: Percentage Completion Method
XYZ continued to work on the JSOM III project in 2008.
On December 31, 2008, XYZs accountant gathered the following details pertaining to the JSOM III building project for 2008.
|
| 2008 |
| Costs incurred during the year | 186 |
| Estimated cost to complete | 264 |
| Invoices raised on UTD during the year | 350 |
| Cash collections from UTD | 330 |
XYZs accounting period is the calendar year and XYZ uses the percentage completion method to recognize revenues.
Required:
- Compute the percentage of completion in 2008 for the JSOM III project.
- Record the transactions for 2008 pertaining to the JSOM III project in XYZs accounting books. Assume that all costs incurred during the year were paid in cash.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock