Question: Exercise 6 - 9 ( Algo ) Variable consideration; estimation and constraint [ LO 6 - 6 ] Thomas Consultants provided Bran Construction with assistance

Exercise 6-9(Algo) Variable consideration; estimation and constraint [LO6-6]
Thomas Consultants provided Bran Construction with assistance in implementing various cost-savings initiatives. Thomass contract specifies that it will receive a flat fee of $58,000 and an additional $28,000 if Bran reaches a prespecified target amount of cost savings. Thomas estimates that there is a 35% chance that Bran will achieve the cost-savings target.