Question: Exercise 6 table [ [ Activities , Duration ( days ) , Immediate Predecessor ( s ) ] , [ A , 4 .

Exercise 6
\table[[Activities,Duration (days),Immediate Predecessor(s)],[A,4.5,-],[B,6.5,A],[C,10,],[D,20,-],[E,16,C],[F,5,C],[G,6,D,F],[H,8,B,G],[I,6,H],[J,2,E,H]]
Given the table above:
1- Construct the PERT chart of this project using the AON representation.
2- Determine the slack (or total float) for each activity. Deduce the critical path.
3- Interpret the slack of activity E.
 Exercise 6 \table[[Activities,Duration (days),Immediate Predecessor(s)],[A,4.5,-],[B,6.5,A],[C,10,],[D,20,-],[E,16,C],[F,5,C],[G,6,D,F],[H,8,B,G],[I,6,H],[J,2,E,H]] Given the table above: 1- Construct