Question: Exercise 6 table [ [ Activities , Duration ( days ) , Immediate Predecessor ( s ) ] , [ A , 4 .
Exercise
tableActivitiesDuration daysImmediate PredecessorsABACDECFCGDFHBGIHJEH
Given the table above:
Construct the PERT chart of this project using the AON representation.
Determine the slack or total float for each activity. Deduce the critical path.
Interpret the slack of activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
