Question: Exercise 7 . 5 A restaurant receives on average 1 , 2 0 0 customers per day ( between 1 0 a . m .

Exercise 7.5 A restaurant receives on average 1,200 customers per day (between
10 a.m. and 10 p.m.). During peak times (12 p.m. to 3 p.m. and 6 p.m. to 9 p.m.), the
restaurant receives around 900 customers in total and, on average, 90 customers can
be found in the restaurant at a given point in time. At non-peak times, the restaurant
receives 300 customers in total and, on average, 30 customers can be found in the
restaurant at a given point in time.
What is the average time that a customer spends in the restaurant during peak
times?
What is the average time that a customer spends in the restaurant during non-peak
times?
The restaurant's premises have a maximum capacity of 110 customers. This
maximum capacity is sometimes reached during peak times. The restaurant
manager expects that the number of customers during peak times will increase
slightly in the coming months. What can the restaurant do to address this issue
without investing in extending its building?
 Exercise 7.5 A restaurant receives on average 1,200 customers per day

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!