Question: Exercise 8-10 Direct Labor and Variable Manufacturing Overhead Variances [LO8-5, LO8-6] Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses

Exercise 8-10 Direct Labor and Variable Manufacturing Overhead Variances [LO8-5, LO8-6]

Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate mp3 player are as follows:

Standard Hours Standard Rate per Hour Standard Cost
27 minutes $5.80 $2.61

During August, 9,425 hours of direct labor time were needed to make 19,300 units of the Jogging Mate. The direct labor cost totaled $52,780 for the month.

Required:
1.

According to the standards, what direct labor cost should have been incurred to make 19,300 units of the Jogging Mate? By how much does this differ from the cost that was incurred? (Round Standard labor time per unit to 2 decimal places.)

Number of units manufactured
Standard labor time per unit
Total standard hours of labor time allowed
Standard direct labor rate per hour
Total standard direct labor cost
Actual direct labor cost
Standard direct labor cost
Total varianceunfavorable

+

2.

Break down the difference in cost from (1) above into a labor rate variance and a labor efficiency variance. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). )

Labor rate variance
Labor efficiency variance

+

3.

The budgeted variable manufacturing overhead rate is $4.1 per direct labor-hour. During August, the company incurred $43,355 in variable manufacturing overhead cost. Compute the variable overhead rate and efficiency variances for the month. (Do not round intermediate calculations and round your final answers to nearest whole dollar. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)

Variable overhead rate variance
Variable overhead efficiency variance

+

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!