Question: Exercise 8-16A Calculating the variable overhead variance LO 8-4, 8-5, 8-6 Adams Company established a predetermined variable overhead cost rate at $10.20 per direct labor
Exercise 8-16A Calculating the variable overhead variance LO 8-4, 8-5, 8-6 Adams Company established a predetermined variable overhead cost rate at $10.20 per direct labor hour. The actual variable overhead cost rate was $9.50 per hour. The planned level of labor activity was 73.400 hours of labor. The company actually used 79,100 hours of labor. Required a. Determine the total flexible budget variable overhead cost variance and indicate the effect of the variance by selecting favorable (F) or unfavorable (U). (Select "None" if there is no effect (i.e., zero variance).) Total flexible budget variable overhead cost variance