Question: EXERCISE-7 A software project uses the time-boxing process model with five stages in each time box. Suppose that each stage takes 8 days. Find the
EXERCISE-7 A software project uses the time-boxing process model with five stages in each time box. Suppose that each stage takes 8 days. Find the number of time boxes if the time required to complete this project is 120 days