Question: EXERCISES Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 9 3 time units?

EXERCISES
Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 93 time units?
\table[[Act. ID,Description,Predecessor,Optm. (a),Most likely (m),Pess. (b),Act time te,Varlance [b-a6]2,Critical],[1,Design package,None,6,12,24,,,],[2,Design product,1,16,19,28,,,],[3,Build package,1,4,7,10,,,],[4,Secure patent,2,24,27,36,,,],[5,Build product,2,17,29,47,,,],[6,Paint,3,4,5,4,7,10,,,],[7,Test market,6,13,16,19,,,]]
 EXERCISES Given the project information in the following table, what is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!