Question: Exercises - Scheduling Progress Score: 7 . 8 / 2 0 3 / 1 0 answered Using the priority list T 4 , T 1

Exercises - Scheduling
Progress
Score: 7.8/203/10 answered
Using the priority list T4,T1,T7,T9,T8,T6,T2,T5,T3, schedule the project below with two processors.
\table[[Task,Time Required,Tasks that must be completed first],[T1,6,],[T2,7,],[T3,9,],[T4,10,T1],[T5,12,T1],[T6,2,T2, T3],[T7,6,T4, T5],[T8,6,T5, T6],[T9,11,T5, T6]]
Task 5 is done by starting at time
Task 8 is done by Select an answer vv starting at time
The finishing time for the schedule is