Question: Expected duration Path Std. Dev. zfor 11 wk. Probability 1-2- 4 +6 = 10 1.14 0.88 .8106 1-3- 3+ 9 = 122.00 -0.50 3085 Given

Expected duration Path Std. Dev. zfor 11 wk.
Expected duration Path Std. Dev. zfor 11 wk. Probability 1-2- 4 +6 = 10 1.14 0.88 .8106 1-3- 3+ 9 = 122.00 -0.50 3085 Given the information provided for a particular project in the table, the probability of completing this project with in 11 weeks is: [Hint: Probability of the completion of the project is the product of the probabilities of completion of all the paths.] 0.8106 0.3085 0.6915 0.2501 None of the above

Step by Step Solution

There are 3 Steps involved in it