Question: expected mean also estimated variance in time for activity E also expected mean for B-E Time estimates Activity Optimistic Most Likely Pessimistic a m b

expected mean also estimated variance in time for
expected mean
also estimated variance in time for activity E
also expected mean for B-E
Time estimates Activity Optimistic Most Likely Pessimistic a m b A 38 50 62 D 19 25 31 F 62 65 68 B 90 99 108 E 91 100 115 85 100 115 A D F Start B E What is the estimated expected (mean) time for activity E? O 100 days 115 days O 99 days 91 days 101 days