Question: explain below a ) Weeks Crashed Path 0 1 2 3 4 5 6 1 - 2 - 3 - 4 - 9 3 5

explain below a)
Weeks Crashed
Path
0
1
2
3
4
5
6
1-2-3-4-9
35* wk.
34*
33*
32*
31*
30*
29*
5-6-8-9
32
32
32
32*
31*
30*
29*
5-7-10-15
20
20
20
20
20
20
19
11-12-13-14-15
33
33
33*
32*
31*
30*
29*
Activity Crashed
4
1
4,13
9,12
9,11
1,5,13
Crash Cost
$15
$18
$20+5
$30+8
$33+10
$22+12+12
Cumul. Crash Cost
$15
$33
$58
$96
$139
$185
*= Critical path
b) The optimum number of weeks to crash the project is four weeks, because after that time the cost to crash one more week ($43,000) would be greater than the indirect cost savings for a week ($40,000).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!