Question: explain below a ) Weeks Crashed Path 0 1 2 3 4 5 6 1 - 2 - 3 - 4 - 9 3 5
explain below a
Weeks Crashed
Path
wk
Activity Crashed
Crash Cost
$
$
$
$
$
$
Cumul. Crash Cost
$
$
$
$
$
$
Critical path
b The optimum number of weeks to crash the project is four weeks, because after that time the cost to crash one more week $ would be greater than the indirect cost savings for a week $