Question: Explain RM scheduling. [Points 5] b. Verify the Schedulability under RM [Points 5] c. Construct the schedule of the following task set with a timing
Explain RM scheduling. [Points 5]
b. Verify the Schedulability under RM [Points 5]
c. Construct the schedule of the following task set with a timing diagram showing task execution for 40 units of time. Give some comments on it. NOTE Task i has to be completed within its period, pi. [Points 5]
| ti | ei, Execution time | pi, Period |
| t1 | 3 | 9 |
| t2 | 2 | 16 |
| t3 | 1 | 15 |
|
|
|
|