Question: Explain the concept of Production Mix Modification strategy by using the following data, which show the time required to process 2 tasks at a manufacturing

  1. Explain the concept of Production Mix Modification strategy by using the following data, which show the time required to process 2 tasks at a manufacturing shop. Provide conclusions on what sequence of production is the best. (4 points)

Task 1: Flow time=6minutes

Task 2: Flow time = 4 minutes