Question: Explain the different parameters to be considered for Financial Estimates and Projections Q . Calculate optimum cost duration Trade off. ( 8 ) ( 1

Explain the different parameters to be considered for Financial Estimates and Projections
Q. Calculate optimum cost duration Trade off.
(8)
(10)
\table[[\table[[Network],[path]],Normal Time,\table[[Normal],[Cost]],Crash Time,\table[[Crash],[Cost]]],[1-2,7,700,4,850],[1-3,5,500,3,700],[1-4,8,600,5,1200],[2-5,9,800,7,1250],[3-5,5,700,3,1000],[3-6,6,1100,5,1300],[4-6,7,1200,5,1450],[5-7,2,400,1,500],[6-7,3,500,2,850]]
Explain the different parameters to be considered