Question: Question 2 of 10. Review the performance metrics from your current program. What can you determine from these metrics? (IMAGE DESCRIPTION: The pefformance metrics

Question 2 of 10. Review the performance metrics from your current program. What can you determine from these metrics? (IMAGE DESCRIPTION: The pefformance metrics for your program show percent complete at 91% and percent spent at 95K) Performance Metric % Complete % Spent Your Program 95% C) The contractor is spending less than budgeted for the work performed. C) The contractor has accomplished less work than planned C) The contractor has accomplished more work than planned C) The contractor is spending more than budgeted for the work performed.