Question: f. As part of restructuring the distribution network, a third-party logistics (3PL) is hired to take the loaded trailers from Process B and deliver it

f. As part of restructuring the distribution network, a third-party logistics (3PL) is hired to take the loaded trailers from Process B and deliver it to customers. Given that the maximum delivery capacity of this 3PL is 25,000 units per day, what is the total output of the restructured distribution network? Identify the bottleneck(s) of this system. (5 Points)
Hint: The priority is to use the internal capacity before utilizing the capacity of the 3PL.
25,000 3PL Output Process A Process B Process C Process D 57,000 60,000 78,000 48,000Step by Step Solution