Question: f) Burndown chart. Given a two-week Sprint (iteration) for a team that has a velocity of 80 story points for a Sprint of 10 working

f) Burndown chart. Given a two-week Sprint (iteration) for a team that has a velocity of 80 story points for a Sprint of 10 working days. It is now the end of day 6. The Daily Scrum Meeting has reported 0, 6, 9, 7, 3, 12 story points done per respective day. Fill in the following table (Day 0 is the starting velocity for the Sprint, and the subsequent values should be for the end of the day) and draw the Sprint Burndown Chart. Then draw the chart (hand-drawn is fine). Sprint Burndown Chart Day Story Points Remaining 0 80 1 2 3 4 5 6 7 8 9 10