Question: f. The following table provides the crash data for this project. The normal times are considered to be deterministic and not probabilistic. Crash the completion
f. The following table provides the crash data for this project. The normal times are considered to be deterministic and not probabilistic. Crash the completion to 28 weeks. What is the normal cost of completion of the project? What is the additional cost of crashing the project to 28 weeks? What activities would have to becrashed (reduced in time) and by how much