Question: f. The lead time for each component (Buy it or make it) is the following: Lead Component Time * The order to Canadian Tire should

f. The lead time for each component (Buy it or
f. The lead time for each component (Buy it or make it) is the following: Lead Component Time * The order to Canadian Tire should be delivered on Nov/30/2020 at Product A 2 days 5:00 PM B 5 days C 5 days Final assembly of Product A should start on D 5 days E 3 Days Assembly B should start on F 3 Days G 3 Days Sub-assembly E should start on H 2 Days 2 Days Component I should start on