Question: facultative pond. [ 4 marks ] ( b ) A waste stabilization pond is designed for a residential estate of 2 5 , 0 0

facultative pond.
[4 marks]
(b) A waste stabilization pond is designed for a residential estate of 25,000 persons each one
generating 0.12m3? person per day of domestic wastewater. The plant consists of a
facultative pond and maturation pond (s), arranged in series. The depths of both ponds are
1.5m and the hydraulic retention time (HRT) of the maturation pond is 5 days. The first-
order BOD removal rate constant at 20C is 0.3 per day. The BOD of raw sewage is 200
mgL, the influent FC is 110tFC100ml and the operating temperature is 18C.
Determine:
(i) The area and hydraulic retention time (HRT) of the ficultative pond. [4 marks]
(ii) The number of maturation pond (s) required to achieve the eflluent FC of 5000100mL.
(iii) The effluent BOD of the maturation pond.
[3 marks]
|3 marks|
facultative pond. [ 4 marks ] ( b ) A waste

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!