Question: failire to find the correct answer will result in a dislike Required information The delivered-equipment cost for a fully equipped CNC machining system is $3.2million.
Required information The delivered-equipment cost for a fully equipped CNC machining system is $3.2million. The direct cost factor is 1.52 and the indirect cost factor is 0.27 . Estimate the total plant cost if the indirect cost factor opplies to the total direct cost. (Enter your answer in dollars and not in millions of dollars) The total plant cost is $