Question: fast answer please A5. Using Preemptive Shortest Job First (SJF) and Priority scheduling algorithms draw their Gantt charts and find their respective average waiting times.

fast answer please A5. Using Preemptive Shortest Job First (SJF) and Priorityfast answer please

A5. Using Preemptive Shortest Job First (SJF) and Priority scheduling algorithms draw their Gantt charts and find their respective average waiting times. The processes are assumed to have arrived in the other P1, P2, P3, P4, P5 all at a time of O milliseconds. [10 marks] Process P1 P2 P3 P4 P5 Arrival Time Burst Time 2 10 4 29 1 3 3 7 5 5