Question: Figure 1.1 shows the process sequence and its respective capacity for making the F104XM product. The company works 5 days a week, single shift 8

Figure 1.1 shows the process sequence and its respective capacity for making the F104XM product. The company works 5 days a week, single shift 8 hours per day.

Mounting 4 units/hr Casting Cutting Facing Painting 5 units/hr 8 units/hr 2 units/hr 4 units/hr Drilling Milling 6 units/hr 4

i) Determine which process becomes a bottleneck when making the above F104XM product. Give your reason.

ii) The capacity of the above bottleneck process is increased by adding one more parallel station. Calculate the maximum weekly capacity (effective) for the overall process.

iii) If the monthly demand for the above product is 800 units, determine how much the total overtime cost the company should bear. Assume that the average overtime cost is RM 25/hour and there are 4 weeks in a month.

Casting 5 units/hr Cutting 8 units/hr Facing 2 units/hr Mounting 4 units/hr Drilling Milling 6 units/hr 4 units/hr Figure 1.1: Process sequence and its capacity to make F104XM product Painting 4 units/hr

Step by Step Solution

3.43 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

A bottleneck is a point of congestion in a production system such as an assembly line or a computer ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock