Question: Figure 3 ( Problem 3 & 4 ) - 3 . Refer to Figure 3 . Which is not true about the PDM for the

Figure 3(Problem 3 & 4)-3. Refer to Figure 3. Which is not true about the PDM for the project? Select the most appropriate one.
a. The late start of Activity A is 1.
b. The early start of Activity B is 5.
c. The late finish of Activity C is 6.
d. The late start of Activity D 7.
4. Refer to Figure 3. Which is not true about the PDM for the project? Select the most appropriate one.
a. The project duration is 9.
b. The total float of C is 0.
c. The free float of B is 0.
d. None of the above is true.
 Figure 3(Problem 3 & 4)-3. Refer to Figure 3. Which is