Question: Figure 5 . 3 7 shows the cross - section of a concrete dam founded on an isotopic layer of silty sand, which is underlain

Figure 5.37 shows the cross-section of a concrete dam founded on an isotopic layer of silty sand, which is underlain by an impermeable layer.
Fig. 5.37
(a) Sketch a flow net and estimate the seepage quantity under the dam on its own.
(b) Sketch two further flow nets for the seepage, after a sheet piling cut-off has been installed: (i) at A-A, and (ii) at B-B.
(c) Comment on the effects of installing the sheet piling cut-off at C-C.