Question: FIGURE 7 . 1 2 Network Diagram for Kitty Condo TABLE 7 . 9 PROJECT ACTIVITY AND COST DATA begin { tabular } {

FIGURE 7.12
Network Diagram for Kitty Condo
TABLE 7.9 PROJECT ACTIVITY AND COST DATA
\begin{tabular}{c|c|c|c|c}
\hline & \multicolumn{2}{|c|}{ NORMAL } & \multicolumn{2}{c}{ CRASH }\\
\hline Activity & Time (days) & Cost (\$) & Time (days) & Cost (\$)\\
\hline A & 12 & 1,300 & 11 & 1,900\\
\hline B & 13 & 1,050 & 9 & 1,500\\
\hline C & 18 & 3,000 & 16 & 4,500\\
\hline D & 9 & 2,000 & 5 & 3,000\\
\hline E & 12 & 650 & 10 & 1,100\\
\hline F & 8 & 700 & 7 & 1,050\\
\hline G & 8 & 1,550 & 6 & 1,950\\
\hline H & 2 & 600 & 1 & 800\\
\hline I & 4 & 2,200 & 2 & 4,000\\
\hline
\end{tabular}
FIGURE 7 . 1 2 Network Diagram for Kitty Condo

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!