Question: Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3. Based on the information provided, what is the expected duration of


Figure 7-3 System Integration Project Consider the System Integration Project depicted in Figure 7-3. Based on the information provided, what is the expected duration of this project? a. 30 days b. 16 days c. 17 days d. 15 days QUESTION 10 Figure 7-4 Lab Experiment Project Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided, what is the expected duration of this project? a. 28 days b. 24 days c. 26 days d. 22 days