Question: Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6. Which activities constitute the critical path for this project network? ADFI

Figure 7-6 Network Scheduling Data Consider the network scheduling data provided in Figure 7-6. Which activities constitute the critical path for this project network? ADFI ACEHI ABEHI ABEG1 RACI Key. (R) Responsible, (A) Approve, (C) Consult, (I) Infom Figure 8-1 RACl Chart Consider the RACI chart presented in Figure 8-1 (RACI stands for Responsible, Approve, Consult, Inform). Who is responsible for development of the specification the project manager the project engineer the contract officer the data manager