Question: Figure below shows the CPM network for a time-constrained project. 05 A (5) 27 58 C(3) 9 12 0 0 START 00 12 | 14

Figure below shows the CPM network for a

Figure below shows the CPM network for a time-constrained project. 05 A (5) 27 58 C(3) 9 12 0 0 START 00 12 | 14 E (2) 12 | 14 07 B (7) 07 7 | 12 D(5) 7 | 12 Which of the activities can be moved on the project timeline to improve resource utilization? Any of the activities A and C only Any of the activities B, D, and E only None of the activities can be moved on the project timeline Any of the activities of A, B, C D and E