Question: fill in the chart below and be sure to include dates with the data fill out the chart provided ensuring 5 day work week with

A contractor has carefully reviewed the plans and specifications for the construction of a small warehouse, identified for the following activities during her work breakdown analysis, and estimated the duration for each activity: Based on the activity logic table provided above, create a schedule for this proiect, using Microsoft Project, Microsoft Excel, or Primavera P6. For your bar chart, you must follow these: (working days: 5 days a week; Non-working days: April 14, May 1, \& June 5). This project will start on April 5, 2023. Complete the table below: N. A contractor has carefully reviewed the plans and specifications for the construction of a small warehouse, identified for the following activities during her work breakdown analysis, and estimated the duration for each activity: Based on the activity logic table provided above, create a schedule for this proiect, using Microsoft Project, Microsoft Excel, or Primavera P6. For your bar chart, you must follow these: (working days: 5 days a week; Non-working days: April 14, May 1, \& June 5). This project will start on April 5, 2023. Complete the table below: N
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts