Question: fill in the missing information: Must show all your work to receive credit. Case A Case B Case C Units Produced 1,000 1,500 800 Standard

fill in the missing information:

Must show all your work to receive credit.

Case A

Case B

Case C

Units Produced

1,000

1,500

800

Standard hours per unit

3.5

?

3

Standard hours for production

?

?

?

Standard rate per hour

$7.25

$7.00

$7.00

Actual hours worked

3,400

4,900

2,330

Actual total labor cost

?

$31,850

?

Labor price variance

$850 F

?

$466 F

Labor usage variance

?

$2,800 U

?