Question: Fill in the table below to show the proper schedule for completing the project in 30 days at minimum cost (i.e., the activity times with

Fill in the table below to show the proper schedule for completing the project in 30
days at minimum cost (i.e., the activity times with crashing for each activity). (Enter your responses as whole numbers.)
| Activity | Time according to schedule (days) | Activity | Time according to schedule (days) |
| A | F | ||
| B | G | ||
| C | H | ||
| D | I | ||
| E |
Calculate the total cost for this project's schedule.
Total costTotal costequals=$ _____. (Enter your response as a whole number.)
The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury cat cage market. Suppose that you are interested in finding ways to speed up the project at minimal additional cost. Determine the schedule for completing the project in 30 days at minimum cost. Penalty and project overhead costs are negligible. Time and cost data for each activity are shown below. Time Time Activity Diagram D Normal Crash (days) Cost ($) (days) Cost ($) 1,300 3,100 1,050 1,270 3,000 4,500 2,000 2,750 11 1,325 700 1,500 1,550 1,700 6009 1,100 2,200 3,800 650 - IO TIMO StartStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
