Question: Fill the table ( blue cells ) only with numeric inputs. What is the project's duration with regular CPM calculation ( using most likely durations
Fill the table blue cells only with numeric inputs.
What is the project's duration with regular CPM calculation using most likely durations
Considering only the crititcal path, what is the probability to finish the project at least days earlier than the project's duration in the last question?
Considering all three paths, what is the duration of the project with at least confidence?
What is teh confidence level probability that you can finish the project under or on budget not going over budget