Question: final answer needed only Table 1 below contains the optimistic time (a), most likely time (m), and pessimistic time (b) based on which the expected

final answer needed only
Table 1 below contains the optimistic time (a), most likely time (m), and pessimistic time (b) based on which the expected time and variance for some activities are calculated and included in the table. Please use the available information to answer questions 16 and 17 Table 1 Activity a m b Expected Variance Time 7 10 17 1 4 820 2 7 MOA 001 12 16 12 1.78 1 3 2 0.11 et 00 E 6 8 22 10 7.11 F 3 4 3 0.11 NIN G 22 2 0 H 6 8 10 8 044 I 4 8 12 8 1.78 011 J 1 2 2 What are the expected time and variance for activity B? 2.2 19.9 8,9 OB,20 2.8Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
