Question: FINANCE 6. The following table shows data for 5 projects of your company Calculate the average production rate experienced on these projects? Project Crew hours/cubic
FINANCE
6.
The following table shows data for 5 projects of your company
Calculate the average production rate experienced on these projects?
| Project | Crew hours/cubic meter | Cubic meter placed |
| 1 | 0.375 | 1200 |
| 2 | 0.680 | 426 |
| 3 | 0.420 | 391 |
| 4 | 0.481 | 288 |
| 5 | 0.555 | 61 |
| a. | 0.531 crew hours/m3 | |
| b. | 0.620 crew hours/m3 | |
| c. | 0.532 crew hours/m3 | |
| d. | 0.465 crew hours/m3 | |
| e. | 0.502 crew hours/m3 |
7.
An increase in WACC of a project already in construction denotes what?
| a. | Decrease in NPV | |
| b. | Increase of profitability of project | |
| c. | Denotes a decrease of valuation of the project | |
| d. | Decrease in project risk | |
| e. | None of the above |
8.
When is the time value of money usually ignored?
| a. | When calculating the Internal Rate of Return (IRR) | |
| b. | Calculating the simple payback period | |
| c. | Calculation of Monetary value and Cash flows from one person to another | |
| d. | Performing Future Value calculations | |
| e. | Salvage value at the end of an investment term |
9.
During review of Estimates, Paretos law can be a useful tool in that
| a. | By carefully selecting the items, the team can review 20% of the cost of the estimate by checking 80% of the items | |
| b. | The team can be certain that the estimate is 80% accurate | |
| c. | Any 20% of the items reviewed will represent 80% of the cost of the estimate | |
| d. | Approximately 80% of the overrun will occur in 20% of the items in the estimate. | |
| e. | All of the above |
10.
You are preparing a Class 5 estimate, what will be the typical maturity level of the project definitions deliverables (expressed as % of complete definition)?
| a. | 1%-5% | |
| b. | 10-40% | |
| c. | 2%-6% | |
| d. | 0%-2% | |
| e. | 2-3% |
11.
You are preparing a Class 5 estimate, you have obtained an equipment quote of R80 000. The Lang Factor is 4.15 for this type of plant. What is the estimated project cost?
| a. | R207 900 | |
| b. | R256 642 | |
| c. | R201 910 | |
| d. | R332 000 | |
| e. | R198 000 |
12.
What is another term for capacity Factor Method?
| a. | Parametric Method | |
| b. | Scale of Operations Method | |
| c. | End-Product Unit Method | |
| d. | Deterministic Method | |
| e. | Bottom-up Method |