Question: Find a workforce plan using the chase strategy without using overtime that allows for no delay in service. 1 2 3 4 Forecasted Demand 3400
Find a workforce plan using the chase strategy without using overtime that allows for no delay in service.
| 1 | 2 | 3 | 4 | |
| Forecasted Demand | 3400 | 5200 | 6500 | 4300 |
| Workforce Level | ||||
| Undertime hours | ||||
| Overtime hours | ||||
| Utilized time hours | ||||
| # of Hires | ||||
| # of Layoffs | ||||
| Utilized time cost | ||||
| Undertime cost | ||||
| Overtime Cost | ||||
| Hiring cost | ||||
| Layoff cost |
What is the work force level for this plan under chase strategy?
| 8, 11, 14, 9 | ||
| 9,13,17,11 | ||
| 9,13,14,11 | ||
| 7, 14, 11, 10 |
What is the undertime hours in the 1st quater?
| 300 | ||
| 400 | ||
| 100 | ||
| 200 |
What is the overtime hours in the 3rd quater?
| 900 | ||
| 200 | ||
| 0 | ||
| 600 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts