Question: Find critical path, Expected time to complete the project? What is the variance of the project completion time? What's the probability of completing in 31
Find critical path, Expected time to complete the project? What is the variance of the project completion time? What's the probability of completing in 31 months?

Problem Set 1 Directions: Consider the following list of activities with time (in months): Activity C D Immediate E F G Predecessor AB H AB D.F E.G Activity Optimistic Most Probable Pessimistic A 3.5 4.0 1.5 2.0 3.0 5.0 C 6.5 7.5 9.0 D 5.0 5.5 6.0 5.0 5.5 8.0 8.0 9.5 10.5 G 6.0 7.0 8.5 H 4.0 4.5 5.5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
