Question: Find critical path, Expected time to complete the project? What is the variance of the project completion time? What's the probability of completing in 31

Find critical path, Expected time to complete the project? What is the variance of the project completion time? What's the probability of completing in 31 months?

Find critical path, Expected time to complete the project? What is the

Problem Set 1 Directions: Consider the following list of activities with time (in months): Activity C D Immediate E F G Predecessor AB H AB D.F E.G Activity Optimistic Most Probable Pessimistic A 3.5 4.0 1.5 2.0 3.0 5.0 C 6.5 7.5 9.0 D 5.0 5.5 6.0 5.0 5.5 8.0 8.0 9.5 10.5 G 6.0 7.0 8.5 H 4.0 4.5 5.5