Question: Find the below: 1. Draw a network diagram 2. Find ES, EF, LS, LF, of each activity 3. List all the paths along with their

Find the below:

1. Draw a network diagram

2. Find ES, EF, LS, LF, of each activity

3. List all the paths along with their durations and specify the critical path and its duration.

4. Identify TF, FF and Span of each Activity

Activity

Duration

Dependency and Lead/ Lag

START

0

-

A

7

START

B

5

START

C

11

A (SS+3)

D

9

B

E

5

A (FS-2)

F

8

A,

G

8

C

H

4

F, G(FF-2)

I

12

D(FS+2), F(FF+3)

J

3

D

FINISH

0

H, I, J