Question: Find the below: 1. Draw a network diagram 2. Find ES, EF, LS, LF, of each activity 3. List all the paths along with their
Find the below:
1. Draw a network diagram
2. Find ES, EF, LS, LF, of each activity
3. List all the paths along with their durations and specify the critical path and its duration.
4. Identify TF, FF and Span of each Activity
| Activity | Duration | Dependency and Lead/ Lag |
| START | 0 | - |
| A | 7 | START |
| B | 5 | START |
| C | 11 | A (SS+3) |
| D | 9 | B |
| E | 5 | A (FS-2) |
| F | 8 | A, |
| G | 8 | C |
| H | 4 | F, G(FF-2) |
| I | 12 | D(FS+2), F(FF+3) |
| J | 3 | D |
| FINISH | 0 | H, I, J |
|
|
|
|